Sunbirddcim com



Download 90.25 Kb.
View original pdf
Page1/2
Date07.01.2023
Size90.25 Kb.
#60308
  1   2
Data Center Migration Checklist


SunbirdDCIM.com | (732) 993-4476 | 200 Cottontail Lane, Somerset, NJ 08873
Job
Aid
Data Center Migration Checklist
1
®
What is a Data Center
Migration?
A data center migration is any movement of data center assets from one location to another. Examples of data center migrations include:
Data Center Migration Checklist
Our Data Center Migration Checklist provides critical but easily forgotten tasks that can reduce risk and downtime in a data center migration. Once a new site for your data center has been selected, use the checklist below to help plan a successful transition—before, during, and after the migration.
Moving to a new data center
Moving some or all assets to a coloca- tion facility
Moving assets from one room or floor to another within the same facility
Migrating applications or services to the cloud
Who should use this checklist?
Anyone who is planning or participating in a data center migration can use this checklist. Examples of roles that can benefit include:
Data Center Migration Managers
Data Center Managers
Data Center Operators
IT Managers
Facilities Managers
Migration Project Planning

Identify and engage all organizational functions/stakeholders that may be impacted by the migration.

Appoint a data center migration manager who is empowered to work across functions, facilitate the migration, communicate progress, and ensure the project’s success.

Develop a migration plan (including budget, timeline, and criteria for success) and obtain buy-in from all stakeholders.

Develop a communication plan to keep all stakeholders apprised of progress.

Gain alignment on roles and responsibilities before, during, and after the project.

Review relevant SLAs and other contracts for terms and conditions, such as early termination penalties, that could impact the migration budget and/or timeline.

Identify the “source of truth” documentation for all parties to work from, such as network drawings, facility diagrams, or databases.
Asset and Application Inventory

Determine if the asset inventory will be completed manually, through discovery software, or a combination of both.

Complete an inventory of hardware and other equipment to determine what needs to be migrated and who owns it.

Complete network connectivity inventory.

Complete an inventory of all applications running on the hardware.

Ensure any previously undocumented hardware, cabling, and applications are accurately inventoried and categorized for moving or decommissioning.

Implement a system using color, alphanumeric tags, labels, or other indicators to uniquely identify what will be moved, where it will be moved, and what connectors or other equip- ment are required for installation.
New Infrastructure Planning

Review the layout of the site to determine where the equipment will be placed.

Create a virtual layout of where the equipment will go and how it will be connected to understand the move outcome. (Use DCIM software to do this quickly and easily.)

Capture network design with the network engineering team and model this information in your source of truth.

Provide the proper cable lengths for all required power and data connections to minimize the possibility of a “spaghetti cabinet” after the migration.

Ensure that your IT deployment aligns with the power capacity designed for each rack and row (both on the initial move date and for future provisioning to reach failover designs).


SunbirdDCIM.com | (732) 993-4476 | 200 Cottontail Lane, Somerset, NJ 08873
Job
Aid
Data Center Migration Checklist

Download 90.25 Kb.

Share with your friends:
  1   2




The database is protected by copyright ©ru.originaldll.com 2024
send message

    Main page